Riders on the Mernda rail trail may notice vehicles on the trail on some occasions during next month.
Works will be occurring intermittently on the Mernda line between Epping and South Morang to allow the Metro Tunnel Project to conduct critical testing of High Capacity Signalling technology.
The works will be overnight, after 7pm.
During the May works at Pindari Avenue, the shared user path that runs alongside the rail corridor between Epping and South Morang station will remain open for use.
However, traffic management will be in place during this period to enable safe movements of light vehicles that will be accessing the path to enter the rail corridor
These works are planned between Monday 17 May and Friday 21 May.
Other works along the rail corridor will continue intermittently during June, July and August.